INSTALLATION INSTRUCTIONS
These instruction have been prepared to assist you with the installation of your Q-duct
Air Distribution System. Although no set of instructions can cover all situations, general
procedures will usually apply. They should be used as a guideline for the specific
situations that exist.
Q-duct are classified as an Air Distribution Device by Underwriters Laboratories, Inc.
meeting the requirements of NFPA90A-1993 Flammability Requirements. Q-duct should be
installed only by qualified technicians familiar with the HVAC equipment and systems
existing at the site. All requirements necessary to produce a safe functional installation
in accordance with all applicable codes, standards, laws, and regulations must be met.
Q-duct are limited to air temperatures that do not exceed 250 degrees Fahrenheit. HVAC
equipment and systems connected to Q-duct must be made to AGA, UL, GAMA, ANSI and all
other applicable Standards which govern the manufacture of HVAC equipment. We recommend
that you become sufficiently familiarized with this information before proceeding with the
installation.
INSPECTION
Inspect your shipment carefully, matching contents to the Packing Slip making sure
everything is present. Note any missing or damaged pieces on the Bill of Lading before
accepting the shipment in order to facilitate a claim for shipping damage.
IDENTIFICATION
Each Q-duct piece is carefully wrapped in plastic. On the outside of the plastic is a
Position Number which identifies the dimension and site location of each piece of the
shipment. Handle the contents in a manner to prevent soiling.
TOOL SUGGESTIONS ( Some or all may be needed)
Approved scaffolding/ladders
Hacksaw
Small crescent wrench
Chalk line
Wire cutters
Nut driver
Tape measure
Hammer & punch
Screw driver manual/electric
Level
Drill
Suspension wire or suspension rail-to-building hardware (such as screws, toggle bolts,
hooks, eyes or beam clamps) are supplied by others.
ROUND Q-duct INSTALLATION
USING CLIPS:
A. Single cable:
- Suspend wire cable across room at proper horizontal height and mount with turnbuckle to
anchor points.
. - Along this cable run mount vertical Strap-ups cables to overhead anchor every 16 ft
and attach to the horizontal cable to maintain its level.
-Attach first section of Q-duct to HVAC source with supplied metal strapping. Continue the
addition of zippered Q-duct sections as supplied.
B. Double cable:
The two cables are suspended (as in 'A.' above) located on either side of the Q-duct
centerline to conform to the Q-duct diameter.
USING RAILS:
USING SINGLE RAILS WITH GLIDERS
A. Take measurements ( from unit, walls, etc.) to establish rail location . Rail should
be located on centerline of Q-duct run. Rail installation must be straight, (use a chalk
line or other device to insure straight alignment)
B. Attach rail to overhead anchor by: (1) using white clips screwed to anchor or (2)
drill holes in rail very three feet and attach with countersunk flat head screws.
C. Attach first Q-duct section to distribution system with clamp provided and slide
Q-duct onto rail using curtain gliders attached to Q-duct, zip sections together.
USING DOUBLE RAIL WITH GLIDERS
A. Take measurements ( from unit, walls, etc.) to establish rail location . Rail should
be located on centerline of Q-duct run. Rail will attach to Strap-up using the gliders.
The gliders will slide in to the upper side of the Double Aluminum rail.
B. Attach Strap-up to ceiling eye-hooks. (supplied by others)
C. Attach first Q-duct section to distribution system with clamp provided and slide
Q-duct onto rail using curtain
D. Rail Installation must be straight, use Double Rail connectors to connect Double
Rail with one another.
E. Slide Q-duct on to rail with curtain gliders attached to Q-duct section, zip section
together.
F. Attach first Q-duct section to distribution system with clamp provided and slide
Q-duct onto rail using curtain gliders attached to Q-duct.
HALF ROUND Q-duct INSTALLATION WITH D-RAIL
A. Take measurement to establish rail location. Each rail should be equal distance from
the center of the Half round Q-duct location. The total distance between the rails should
be equal to the distance between the plastic channels on the flat top side of the Q-duct
B. Installation must be straight.
C. Attach rail to ceiling by drilling holes in rail every 3.ft and screw to ceiling in
location which provides suitable strength for mounting Q-duct.
D. Slide Q-duct on to Rail, zip section together .
E. Attach Q-duct to sheet metal ducting with clamp supplied by Q-duct.
Caution and Warning: Q-duct air distribution systems is only for use as described in
the brochure and catalog published by Q-duct, Inc. All other use is without any liability
for Q-duct, Inc. This product may only be installed by qualified installer who is familiar
with the HVAC system Q-duct is being attached to , and who thoroughly understands
requirements for a safe installation that is in compliance with all applicable laws, codes
and regulations. |